A current transformer (CT) steps a large AC current down to a small secondary current, usually 5 A or 1 A, for energy meters and protection relays. A current transducer converts current into a standard signal such as 4–20 mA, 0–10 V or a Modbus value for a PLC, SCADA system or building controller.
The device on the receiving end decides which one you need. An energy meter needs a current signal that keeps the waveform, which a current transducer’s 4–20 mA output does not. A standard PLC analogue input is not built to take a 5 A secondary.
What Is the Difference Between a Current Transducer and a Current Transformer?
A current transformer reproduces the primary current at a fixed ratio, while a current transducer turns a measured quantity into a signal a control system can read. IEC 61869-2 covers the first, and IEC 60688 covers the second while explicitly excluding instrument transformers.
Datasheets blur the line. Some suppliers call Hall-effect sensors “current transducers”, and many buyers search for “current sensor vs current transformer” with the same question in mind. The table separates the three families you will meet.
| Feature | Current transformer | Signal transducer | Hall-effect or fluxgate transducer |
|---|---|---|---|
| Output | Secondary current at a fixed ratio, usually 5 A or 1 A | A processed value: 4–20 mA, 0–10 V or a Modbus register | A scaled copy of the instantaneous current, as a small current or voltage |
| AC or DC | AC only | AC or DC, depending on the model | AC and DC |
| Power supply | None (passive) | Usually an auxiliary supply or loop power | Auxiliary supply |
| Open output | On a current-output CT, dangerous voltage across an open secondary while the primary carries current | Output signal drops out; a CT feeding its input keeps the CT hazard | Signal drops out |
| Typical receiver | Energy meters, protection relays, panel meters | PLCs, SCADA, building controls, data loggers | Inverters, chargers, drives, DC monitoring, power analysers |

Current Transformer
The primary conductor passes through a magnetic core, and a secondary winding with many turns delivers a current that follows the primary at the rated ratio. A 400/5 A CT, for example, gives 5 A when 400 A flows. Three ratings decide whether a CT suits the device it feeds:
- The rated ratio and secondary, 5 A or 1 A, which must match the receiving input.
- The burden in VA, which the meter, relay and connecting leads share and must not exceed if the CT is to hold its class.
- The accuracy class, where IEC 61869-2 sets measuring classes such as 0.2S and 0.5S and protective classes such as 5P and 10P.
Treat the secondary of a current-output CT as a current source. Opening it while the primary carries current can put a high voltage across the terminals. Short it at the shorting links or test terminal block before you disconnect a meter or relay. Voltage-output CTs differ: an internal burden resistor turns the secondary current into a low voltage, commonly 333 mV, and they connect only to meter inputs built for that voltage.

Current Transducer
A signal transducer measures current and outputs a value a controller can scale directly. IEC 60688 covers these devices, and the analogue DC current signals they send fall under IEC 60381-1. The 4–20 mA loop is common because its live zero lets the controller tell a true zero (4 mA) from a broken wire (0 mA).
Many AC current transducers take the 5 A or 1 A secondary of an existing CT as their input, so the two devices often work in series. Hall-effect and fluxgate transducers, a second family, output a copy of the instantaneous current, including DC; the DC section covers them.
When to Use a Current Transformer or a Current Transducer
Choose by the input of the device that will read the signal, then size the sensor to the circuit. Energy meters and protection relays take CT secondaries, while control systems take process signals.
Energy Meters
An energy meter needs a 5 A or 1 A CT secondary, a low-voltage signal it is designed for, or a direct connection. It multiplies instantaneous voltage and current to get instantaneous power, then integrates that power over time to give kWh. A current transducer’s 4–20 mA output carries an RMS or averaged current with no voltage or phase information, so a meter cannot calculate active energy from it. Active power transducers with a 4–20 mA output scaled in kW do exist, and a control system can integrate that signal. The result is a monitoring value, not a reading approved for billing.
Before you order CTs for a meter:
- Match the CT secondary to the meter’s current input, for example an x/5 A CT on a 5 A input.
- Choose a CT accuracy class that suits the metering accuracy the project needs.
- Keep the meter’s current-circuit consumption plus lead losses within the CT’s rated burden.
- Check whether the load stays below a direct-connected meter’s maximum current, because then no CT is needed.
- Consider Rogowski coils for high currents or crowded busbars, with an external integrator or a meter designed for their output.

PLCs, SCADA and Building Controls
These systems read 4–20 mA, 0–10 V or Modbus, so a signal transducer sits between the circuit and the controller, often fed from an existing CT. Match the PLC scaling to the transducer’s range, check loop power, and read accuracy as a percentage of span. Averaging inside the transducer also slows its response.
When the controller also needs voltage, power or kWh, we would first check for a Modbus RTU port. One energy meter on RS485 can then replace the transducer and deliver all of those values over a single pair of wires.

Protection Relays
Protection relays take CT secondaries too, but from protective-class cores rather than metering cores:
| Feature | Measuring CT | Protective CT |
|---|---|---|
| Example classes | 0.2S, 0.5S | 5P, 10P |
| Accurate over | The specified measurement range and burden conditions | The specified protection range, such as up to 10 times rated current for 5P10 at rated burden |
| During a fault | May saturate; meter protection depends on the specified instrument security factor (FS) and actual burden | Designed to hold its composite error within the class limit at the rated accuracy limit primary current under the specified burden and steady-state test conditions |
| Typical receiver | Energy meters, panel meters | Protection relays |
Where one CT has to serve both jobs, specify separate metering and protection cores. Signal transducers are built for monitoring, and their output ranges and response times do not suit fault detection.

Can a Current Transformer Measure DC?
No. A conventional inductive CT needs a changing magnetic flux, and IEC 61869-2 covers inductive CTs for rated frequencies from 15 to 100 Hz. Steady DC produces no secondary current, and a DC component on an AC current can push the core towards saturation. DC circuits in PV, battery systems and DC charging need one of the two methods below.
Hall-Effect and Fluxgate Transducers
All three common types need an auxiliary supply, and some add a 4–20 mA or 0–10 V output stage for direct connection to a PLC. They differ mainly in how they handle offset and drift:
| Type | How it works | Trade-off |
|---|---|---|
| Open-loop Hall | A Hall sensor in a gap in the core; its output is amplified | Simple and compact, with more offset and temperature drift |
| Closed-loop Hall | A compensation winding cancels the core flux | Generally better linearity and accuracy, with a higher supply current |
| Fluxgate | A saturating core detects the flux | Used where DC accuracy and low offset matter most |
DC Shunts
A shunt is a precision resistor in series with the load whose voltage drop follows the current, and a DC energy meter measures that drop with the line voltage. Our DC energy meters use an integrated or an external 75 mV shunt. Before you specify one:
- Match the shunt’s rated drop to the meter input, for example a 75 mV shunt for a 75 mV input.
- Size the shunt’s current rating to the circuit, since it carries the full load current.
- Allow for the heat it dissipates when you plan mounting and spacing.

Common CT and Transducer Installation Mistakes
Most problems with CTs and transducers show up at commissioning, and each one has a clear signature:
| Mistake | What happens | Fix |
|---|---|---|
| Opening a current-output CT secondary while the primary is live | High voltage at the terminals; risk of shock and damage to the CT | Short the secondary at the shorting links before you disconnect anything |
| Wiring an x/1 A CT to a 5 A meter input | The meter runs at a fifth of its rated input, and readings are wrong if the ratio is entered as x/5 | Order CTs with the secondary the meter expects |
| Connecting a 333 mV CT to a 1 A or 5 A current input | Readings far below the true value, because the input is a low-resistance current path | Use a meter with a matching voltage input, or a current-output CT |
| Entering the CT ratio in both the meter and the SCADA system | Every value is scaled twice | Apply the ratio in one place and record where |
| Reversing CT polarity or pairing a CT with the wrong phase voltage | Negative or low power per phase; export appears as import | Face P1 towards the supply, match each CT to its phase and check per-phase power factor |
| Scaling the PLC to the wrong transducer range | A 0–200 A transducer scaled as 0–100 A halves every reading: 12 mA shows 50 A instead of 100 A | Copy the range from the transducer label and test at a known current |

YTL Meters for CT, Rogowski and Shunt Inputs
Our standard range has no signal transducers; it covers the meters that read CT, Rogowski and shunt inputs, plus direct-connected meters that need no sensor up to their rated current. Every AC meter below communicates over RS485 Modbus RTU, so a PLC or SCADA system can poll it without a separate transducer.
| Input | YTL model | What to confirm |
|---|---|---|
| CT, 5 A secondary | DEM3K302: three-phase CT/PT-operated, CT input 5(6) A, CT ratio up to 2000:1, PT ratio up to 350:1, RS485 Modbus RTU | CT secondary of 5 A, a ratio inside the meter’s range, and the required IEC/EN accuracy class on the datasheet or certificate |
| Direct, three-phase up to 100 A | DEM3A302: three-phase direct connection, 54 mm module width | Maximum current per phase |
| Direct, single-phase up to 100 A | DEM2A302: single-phase direct connection, 36 mm module width | Maximum current |
| Rogowski coil | M60333: three-phase DIN-rail meter for external Rogowski coils, Imax 600 A, up to 2400 A depending on the coil selected | Coil model and meter pairing |
| DC shunt | DC02NC-S1: DC 100–1000 V, external 75 mV shunt up to 2000 A, Class 1 to IEC 62053-41 | Shunt rating and system voltage |

Where a project calls for MID-covered meters, the DEM3K302 is covered by EU type-examination certificate 0598/MID/B/26/010 under the Measuring Instruments Directive 2014/32/EU (Module B), issued by SGS Fimko Oy, Notified Body 0598. Ask us for the full certificate and the declaration of conformity for your variant, and confirm with the network operator or supplier what it accepts for billing at your site.
Send us these details and we can match a meter to your sensors:
- Circuit type: single-phase, three-phase four-wire or three-phase three-wire.
- Maximum current, plus the CT ratio and secondary rating if CTs are already installed.
- The system that will read the data: the meter display, a PLC or SCADA system over Modbus RTU, or a billing platform.
- Whether you need the Modbus register map for the exact model and firmware.
- Whether the project needs MID-covered metering, and the target country.
- Quantity and any module-width limit inside the enclosure.
FAQ
Is a Current Transducer More Accurate Than a Current Transformer?
Neither type is more accurate by default, because the figures measure different things. A CT class under IEC 61869-2 limits ratio error and phase displacement at rated burden, while a transducer quotes error as a percentage of span. For metering, the system error combines the CT’s ratio and phase errors at its actual burden with the meter’s own error, so check the CT class against the project’s metering specification. A meter’s MID certificate covers the meter, not the external CT.
Can One CT Feed Both an Energy Meter and a Transducer?
Yes, provided both current inputs are wired in series on the CT secondary and the combined burden of the meter, transducer and leads stays within the CT’s rating. Parallel wiring splits the current and makes both readings wrong. On billing circuits, check the project rules first, since some require a dedicated, sealed metering CT.
How Do I Size the CT Primary for an Energy Meter?
Choose a primary rating that covers the expected current within the CT’s measurement range and accuracy requirements; the CT rating does not set the feeder’s load capacity. For example, a feeder at 250 A with 320 A peaks could use a 400/5 A CT. Enter the same ratio in the meter and confirm the meter supports it.
Sources
- IEC 61869-2:2012 Instrument transformers – Part 2: Additional requirements for current transformers, IEC: scope of inductive current transformers for measuring instruments and protective devices at rated frequencies of 15 to 100 Hz (Edition 1.0).
- IEC 60688:2024 Electrical measuring transducers for converting AC and DC electrical quantities to analogue or digital signals, IEC: definition of measuring transducers with analogue or digital outputs for AC and DC inputs, and exclusion of IEC 61869 instrument transformers.
- IEC 60381-1:1982 Analogue signals for process control systems. Part 1: Direct current signals, IEC: analogue DC current signals used between elements of industrial-process measurement and control systems (Edition 2.0).