Current Transformer vs Potential Transformer: 5 A or 100 V?

By

Window-type current transformer and cast-resin potential transformer

A current transformer (CT) is wired in series with the conductor and scales high current down to a 5 A or 1 A secondary. A potential transformer (PT), called a voltage transformer (VT) in IEC standards, is wired in parallel across the supply and scales high voltage down to a 100 V or 110 V secondary.

An AC energy meter needs both signals: it multiplies voltage and current into active power and integrates that power over time to register kilowatt-hours (kWh). Fit CTs when the current exceeds the meter’s direct rating, PTs when the voltage does, and typically both on medium-voltage feeders. The two transformers then need opposite secondary-circuit rules.

How Do a Current Transformer and a Potential Transformer Differ?

Both are inductive instrument transformers that isolate the primary circuit from the meter inputs, but their connection, turns ratio and normal secondary state are the reverse of each other.

ParameterCurrent transformer (CT)Potential or voltage transformer (PT / VT)
Quantity measuredAlternating currentAlternating voltage
Primary connectionIn series with the load conductor or busbarIn parallel, phase-to-phase or phase-to-neutral
Primary vs secondary turnsFewer primary turns, more secondary turnsMore primary turns, fewer secondary turns
Typical secondary rating5 A or 1 A100 V or 110 V line-to-line (57.7 V or 63.5 V phase-to-neutral)
Normal secondary stateClose to a short circuit through the low meter impedanceClose to an open circuit into the high meter impedance
Main secondary hazardOpening the secondary under loadShort-circuiting the secondary
IEC standardIEC 61869-2 (inductive CTs)IEC 61869-3 (inductive VTs)
CT series and PT parallel connections to energy meter inputs

Current Transformer 5 A or 1 A Secondary

A measuring CT acts as a current source driven by the primary load. A 400/5 A CT (ratio 80:1) delivers 5 A on its secondary when 400 A flows in the busbar.

  • 5 A secondary: the usual match for CT-operated DIN-rail meters with a 5(6) A input (5 A basic current, 6 A maximum).
  • 1 A secondary: the choice for long secondary runs, where cable losses at 5 A would add too much burden.

Voltage Transformer (PT) 100 V or 110 V Secondary

A PT steps the system voltage down by a fixed turns ratio and feeds the high-impedance voltage inputs of the meter, so its secondary current stays small.

  • Three-wire systems: 100 V or 110 V line-to-line, the standard secondary values IEC 61869-3 gives for European practice.
  • Four-wire (3P4W) systems: 57.7/100 V or 63.5/110 V, where 57.7 V is 100 V divided by √3.

Why Are CT and PT Wiring and Safety Rules Opposite?

A CT works into a near short circuit and a PT into a near open circuit, so their secondary protection and isolation rules run in opposite directions. Testing or isolating instrument-transformer circuits is work for qualified electricians, following the site’s isolation procedure for the primary circuit.

Open CT and shorted PT secondary circuit diagrams

Series CT Wiring and Open-Circuit Risk

The primary load sets the CT current, whatever happens on the secondary side. In normal operation the secondary ampere-turns cancel most of the core flux. If the secondary is opened under load, all the primary ampere-turns become magnetising force, which saturates the core and induces hazardous peak voltages at the open terminals.

  • Do not install ordinary fuses or disconnecting devices that could leave a current-output CT secondary open while primary current is flowing.
  • Use approved CT shorting terminal blocks or test switches designed for safe meter testing and isolation, following the manufacturer’s instructions and the site’s electrical safety procedures.

Parallel PT Wiring and Short-Circuit Risk

A PT secondary behaves as a stiff voltage source limited mainly by its winding impedance. A short circuit across its terminals drives a high fault current that overheats the windings and can cause internal arcing.

  • Provide appropriate primary and secondary protection for the PT circuits as specified by the switchgear design and applicable requirements.
  • Do not short-circuit the PT secondary.

Shared Three-Phase CT and PT Wiring Checks

The protection rules are opposite, yet every three-phase CT and PT installation needs the same three checks before energising:

  • Match each current input (I1, I2, I3) to its own voltage phase (U1, U2, U3), so that active power and power factor read correctly.
  • Fit every CT with P1 towards the supply and P2 towards the load, with S1 and S2 wired the same way on each phase, so that import is not recorded as export.
  • Follow the approved secondary-circuit earthing arrangement, the meter and instrument-transformer manufacturers’ wiring instructions, and applicable local requirements. Where secondary earthing is required, use the designated single-point connection and avoid unintended multiple earth connections.

When Does an Energy Meter Need a CT, a PT or Both?

Two thresholds decide the wiring: feeder current above the meter’s direct current rating calls for CTs, and system voltage above its voltage rating calls for PTs. A 3×230/400 V circuit up to 100 A can be wired straight into a 100 A direct-connected meter with no external transformers.

Low-Voltage High-Current CT-Only Metering

European 230/400 V feeders above 100 A stay within the meter’s voltage rating. The phase voltages connect straight to the meter, and only the current passes through CTs, usually with a 5 A secondary to match a 5(6) A meter input. Where a busbar is too wide for a CT window or the conductor cannot be disconnected, a Rogowski coil wraps around the conductor and measures AC current with no iron core to saturate. Fitting it still follows the site’s isolation procedure.

Copper busbar through a window CT in low-voltage switchgear

Medium- and High-Voltage CT-PT Circuits

Medium- and high-voltage feeders normally require instrument transformers or other approved sensing arrangements to provide compatible current and voltage signals to the energy meter.

  • Three-phase four-wire systems: three-element metering typically uses three CTs and three corresponding phase-to-neutral voltage measurements, provided through suitable VTs where required.
  • Three-phase three-wire systems: two-element Aron metering may use two CTs and two line-to-line voltage measurements, with suitable VTs where required.

The system earthing arrangement, transformer connections, insulation requirements and meter wiring must follow the approved switchgear design and applicable metering requirements.

Cast-resin voltage transformers on a withdrawn medium-voltage switchgear tray

Combined CT and PT Ratio Calculation

With both transformers fitted, the primary multiplier is the CT ratio times the PT ratio.

  • Worked example: a 1000/5 A CT (200:1) with a 10 kV/100 V PT (100:1) gives a multiplier of 20,000, so 0.5 kWh measured on the secondary side equals 10,000 kWh on the primary side.
  • Programming check: confirm whether the meter applies both ratios internally and displays primary kWh, and that the product of the two ratios stays within the meter’s programmable maximum.
CT and PT ratio calculation for a 20,000× energy metering multiplier

What Accuracy, Burden and Compliance Limits Apply to CT and PT Metering?

Scaling the signals to 5 A and 100 V does not by itself make the metering accurate or legally valid. The result depends on the IEC 61869 accuracy classes, the burden on each secondary circuit and what the MID covers.

CT and PT Metering Accuracy Under IEC 61869

IEC 61869-2 covers inductive CTs for rated frequencies from 15 Hz to 100 Hz, and IEC 61869-3 covers inductive VTs; the two standards treat light load differently.

  • Inductive CTs (IEC 61869-2): measuring classes such as 0.2, 0.5 and 1 set error limits from 5% to 120% of rated current.
  • Special CT classes 0.2S and 0.5S: the limits extend down to 1% of rated current, which suits billing points with light overnight loads.
  • Inductive VTs (IEC 61869-3): measuring classes 0.1 to 3 set error limits from 80% to 120% of rated voltage, and the standard has no S class.

CT and PT Secondary Burden and Cable Limits

Burden is the total load on the secondary terminals in VA or ohms: the meter input, the terminals and the cable run out and back.

  • Cable loss: cable burden follows I²R, so a 5 A loop adds 25 times the cable burden of a 1 A loop on the same cable ((5 ÷ 1)² = 25).
  • Burden range: IEC 61869-2 and IEC 61869-3 state each accuracy class over a defined burden range, not at any burden.
  • Under-burden: a digital meter on short leads can load a CT or VT well below its rated burden, so specify a rated burden or extended burden range that matches the real loop.
CT secondary cable burden at 1 A and 5 A with equal loop resistance

EU MID Scope for CT and PT Meters

For regulated tenant sub-billing and customer invoicing in the European Union, check whether the Measuring Instruments Directive (MID) applies to the billing and what it covers before buying hardware.

  • Meter scope: Annex V (MI-003) of Directive 2014/32/EU covers active electrical energy meters and states that it does not cover the instrument transformers used with them.
  • National rules: confirm any separate approval or verification requirements for external CTs and VTs in the target market. Great Britain and Northern Ireland have different applicable metering arrangements, which should be checked separately.

Which YTL DIN-Rail Meters Support CT and PT Inputs?

We supply 54 mm (three-module) DIN-rail energy meters for 5(6) A CT inputs with PT ratio settings, for Rogowski coils, and for direct connection up to 100 A. Our catalogue does not include voltage transformers, so specify the PT with the switchgear.

YTL modelConnection and wiringCurrent inputCT and PT ratio rangeInterface and accuracy
DEM3K302External CT and PT; 3P4W 3×57.7/100 V to 3×230/400 V; 3P3W (Aron) 3×100 V to 3×400 V5(6) A CT (Ib 5 A, Imin 0.05 A)CT up to 2000:1; PT up to 350:1; CT × PT up to 350,000:1RS485 Modbus RTU and DL/T 645-2007; ≤75 ms RS485 communication refresh; specified Class 0.5S active-energy accuracy; EN 50470-3:2022 Class C EU type-examination coverage; 4-tariff TOU with real-time clock
DEM3K304External CT and PT; same voltage ranges and wiring as the DEM3K3025(6) A CT (Ib 5 A, Imin 0.05 A)CT up to 2000:1; PT up to 350:1; CT × PT up to 350,000:1Wired M-Bus (EN 13757-3, 2400 bps); Class 0.5S (IEC 62053-22); 4-tariff TOU
M60333External Rogowski coil; direct voltage or PT; 3P4WRogowski, Ib 20 A, Imax 600 A (up to 2,400 A by coil)PT up to 350:1; the rated voltage range does not reach 57.7/100 V or 63.5/110 V, so confirm the PT secondary with usRS485 Modbus RTU and DL/T 645-2007, ≤75 ms RS485 communication refresh; specified active-energy accuracy: Class 1; Class B as listed in the product specification; 4-tariff TOU
DEM3A302Direct connection; 3P4W or 3P3W up to 3×230/400 VDirect, up to 100 ANot applicableRS485 Modbus RTU and DL/T 645-2007, ≤75 ms RS485 communication refresh; Class 0.5 (IEC 62053-21), Class C (EN 50470-3); 4-tariff TOU
YTL DEM3K304 energy meter and switchboard DIN rail

Scope Notes and MID Certificate Verification

Check the model list on the certificate before ordering meters for billing, and ask us for the full certificate and the declaration of conformity for your variant. Our certificates by model series are a starting point for that check.

  • The DEM3K001, DEM3K202 and DEM3K302 are covered by EU type-examination certificate 0598/MID/B/26/010 under the MID (Module B), issued by SGS Fimko Oy, Notified Body 0598.
  • The DEM3A001, DEM3A202 and DEM3A302 are covered by certificate 0598/MID/B/26/011 from the same notified body.
  • For the M-Bus DEM3K304, ask us for the certificate that covers it before planning billing use.

Module B covers the examined meter type and does not by itself establish completion of the full conformity assessment. For regulated billing applications, confirm the applicable conformity documentation and EU Declaration of Conformity for the supplied instrument, together with any separate national requirements for external CTs and VTs.

Project Checklist for YTL Engineering

Send these details with your request for model matching or a quotation:

  • Primary voltage and PT secondary rating (57.7/100 V, 63.5/110 V, 100 V, 110 V, or direct 230/400 V)
  • System wiring (3P4W or 3P3W Aron)
  • Maximum primary current, sensor choice (5 A CT or Rogowski coil) and planned CT and PT ratios
  • Communication (RS485 Modbus RTU, M-Bus or SO pulse output) and tariff rules
  • Destination country, and whether the readings serve internal monitoring or regulated billing

FAQ

Can CTs or PTs Measure Steady DC Circuits?

No. Inductive CTs and PTs need a changing magnetic flux, so a steady DC current or voltage induces no continuous output, and a DC bias pushes the iron core towards saturation. PV strings, battery banks and DC fast chargers need a DC energy meter built around a shunt or a DC current sensor, with accuracy classes set by IEC 62053-41.

Can an Energy Meter Share Existing Protection CTs or PTs?

A protection CT core such as 5P20 should not automatically be used for precision energy metering. The designation specifies a 5% composite-error limit at 20 times rated primary current under the applicable rated-burden and test conditions. Its accuracy characteristics may not satisfy the required metering accuracy across the normal operating range. During faults, the secondary current may also exceed the energy meter’s permitted input limits. Where appropriate, specify a separate metering core or a suitable dedicated metering CT. Sharing a VT secondary may be acceptable if the voltage accuracy, combined burden, circuit protection and applicable metering or sealing requirements are satisfied.

What Happens If You Connect 1 A CTs to a 5 A Meter?

A 1 A CT uses a smaller portion of the nominal input range of a meter rated for 5 A CTs. For example, the DEM3K302 specifies a 5(6) A CT input and a minimum current of 0.05 A. This corresponds to 1% of a 5 A secondary rating but 5% of a 1 A secondary rating. However, this comparison does not establish compatibility or guaranteed accuracy with a 1 A CT. The meter’s supported ratio configuration, input characteristics and accuracy under the intended operating conditions must be confirmed. For the DEM3K302, select a compatible 5 A CT secondary unless YTL confirms another supported configuration for the exact model.

Source

Back to Knowledge Center

Need a Smart Metering Solution for Your Project?

Tell us your requirements and our team will provide a professional solution and quotation within 24 hours.

Quick ResponseReply within 24 hours
Expert SupportEngineer-to-engineer
Custom SolutionsProject-ready from spec
Long-term PartnerSingle point of contact
Add Project Details (Optional)

Share technical or purchasing details to help us recommend the right model faster.

By submitting this form, you ask YTL to use your details to respond to your inquiry. Privacy Policy

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.